Regulator confirms new life in Terra Nova

Ashley Fitzpatrick
Send to a friend

Send this article to a friend.

Offshore regulator expects another 87 million barrels

The Terra Nova FPSO sails across Mortier Bay in this file photo. It has been confirmed that the Terra Nova oilfield will get an extended life. Production is expected to continue until 2027. — Southern Gazette file photo

Provincial coffers took a hit when the production vessel at the Terra Nova oilfield was taken offline for repairs in 2012. However, the work has resulted in new benefits for both the province and the oil companies involved.

Specifically, it means an additional 87 million barrels of oil from Terra Nova, sources at the Canada-Newfoundland and Labrador Offshore Petroleum Board (CNLOPB) have confirmed.

The Terra Nova floating production, storage and off-loading vessel (FPSO) was taken offline and work on that ship was completed in Marystown over the course of 183 days in 2012 — from mid-June to early December.

Paired with spending on work at the field, the vessel’s new life is expected to result in a longer life for the project overall.

“The swivel (on the FPSO) needed upgrades, as well as the flowlines needed to be improved, so they were all replaced. And once those improvements were done, we felt comfortable to look at the analysis and say you can extend that (field) life out for another seven years,” said Jeff O’Keefe, the CNLOPB’s manager of resource management.

The additional production is expected to come in large part as a result of this extended service life for the oil project.

Life extended until 2027

The regulator expects the oilfield will now be in operation until at least 2027, extended from the previous end-life estimate of 2020.

The regulator’s estimate for the total expected production from the field has jumped

from 419 million barrels of oil to 506 million barrels.

“While there is a Southern satellite piece ... it’s more on the fact they can produce over a longer period of time and, thus, the recovery factor increases,” O’Keefe said.

“You have a confidence that they can produce a certain amount and, basically, once this equipment was added and all the upgrades were done, then we had the confidence to say they can go out and proceed (to 2027).”

The board has closely monitored production at Terra Nova in February and March, considering how the field has been producing upon the FPSO’s return.

See ALL PROJECTS, page D2

All projects expected to produce more oil  

The Terra Nova field was discovered in 1984 and became the second oilfield to be developed after Hibernia. About 350 kilometres from St. John’s, the project is led by Suncor Energy.

In all, 1,198 people were working on the Terra Nova oil project as of Dec. 31, 2012.

According to O’Keefe, the added production at Terra Nova was made known to the province about mid-March.

Without the same time offline this year, the provincial government is expecting Terra Nova to produce about 15.3 million barrels of oil this year. It is 6.8 million barrels more than in 2012.

Total oil production for all projects in the province is expected to be 84.4 million barrels — a 16.9 per cent increase over 2012.

afitzpatrick@thetelegram.com

Organizations: Canada-Newfoundland and Labrador Offshore Petroleum Board

Geographic location: Terra Nova, Marystown

  • 1
  • 2
  • 3
  • 4
  • 5

Thanks for voting!

Top of page

Comments

Comments

Recent comments

  • GS
    April 03, 2013 - 13:24

    Makes you wonder why we do not have more of these oil producing facilities. You cannot bring Hibernia back in shore to extend its life and you won't be able to bring Hebron back either. We are here for the long haul and these types of facilities can improve that.