Around the Bay d’Espoir power plant

Ashley
Ashley Fitzpatrick
Send to a friend

Send this article to a friend.

More than 45 years in, power megaproject remains a valuable generator

The 75-megawatt turbine stirs the air inside the access pit, while a steady whirr penetrates the standard-issue orange foam earplugs, handed out at the Bay d’Espoir hydroelectric generating station.

The main powerhouse at the Bay d’Espoir hydroelectric generating station. This powerhouse contains the Bay d’Espoir control centre and six of its seven generating units. A station switchyard is visible behind. A second powerhouse, housing the station’s seventh generator, was built after the first and is not visible in the photo. — Photos by Ashley Fitzpatrick/The Telegram

The turbine generator is one of six found in the belly of the main powerhouse at Bay d’Espoir — the hydro power plant that, after its official opening by Joey Smallwood in August 1967, permitted both rapid industrial growth and the electrification of rural Newfoundland.

Power demand on the growing isolated island electrical system led to a second powerhouse with a

154-megawatt turbine, officially opened by Brian Peckford in February 1978.

If the electrical power control centre in St. John’s is the nerve centre for the island power system, the power plant at Bay d’Espoir — even today — remains its beating heart.

With a little more than 600 megawatts of capacity, the Bay d’Espoir power plant is the largest on the island, coming in ahead of the 500 megawatts produced from burning oil in Holyrood.

Provincially, it is the second-largest power facility, ranking behind the 5,428-megawatt capacity of Churchill Falls in Labrador.

                          •••

A level above the floor of the powerhouse, in a much brighter room, a phone rings.

“Control room? Yes. She’s at 71 … 72,” says hydro plant operator Darrin Hicks upon answering, reading from a display in front of him.

Hicks is the lead operator at Bay d’Espoir and has 24 years on the job with Newfoundland and Labrador Hydro.

During The Telegram’s Oct. 8 visit, he sits at a desk positioned across from controls that have been with the company for more than 20 years longer than he has.

“This is like a museum,” he says with a laugh, “but if it works, why change it?”

Upgrades are, particularly these days, under heavy scrutiny, in light of Newfoundland and Labrador Hydro’s rising capital budgets and the resulting discomfort from industrial customers, the Consumer Advocate and the Public Utilities Board.

The Telegram will be looking more closely at Hydro’s projects in the weeks to come.

Hicks explains the station has seen upgrades to equipment over the years as required, pointing out clearly newer additions to the control panels. Computer screens stand on his desktop.

His job involves collaboration with the electric power control centre in St. John’s — making sure generators are kept at the ready and brought on and off as the power demands of the province change.

“They need them started, up to speed and then synced to the system,” he said, explaining the units can be turned up and down from St. John’s, but no one there can get them going, or troubleshoot.

                          •••

Outside and uphill, in a steady wind and already crisp temperatures, power systems operator apprentice Jessica Lowe steps out of a Nalcor-labelled, heavy-duty pickup, capable of handling the deep ruts and potholes of a dirt access road.

Lowe took up the task of being the tour guide, offering a stop at the intake at the reservoir, to provide a broader view of the Bay d’Espoir infrastructure — switchyard, powerhouses, transmission lines.

Buried penstock pipes connect the collected water to the powerhouses and turbines about 180 metres below. Bay d’Espoir’s three trademark “surge tanks,” essentially emergency water release valves, stand between.   

Lowe explains the large drop-down gates at the upper intake can block the water from running down through the pipes, towards the powerhouse. These allow for maintenance work as needed.

The Bay d’Espoir power plant can be the third stop for water in the system, with power also being generated at the Granite Canal power station and Upper Salmon, before reaching Bay d’Espoir and running out towards St. Veronica’s, Milltown-Head of Bay d’Espoir, St. Alban’s and other communities in the distance.

                          •••

The construction of the power infrastructure at Bay d’Espoir was the high-risk, high-reward project of its time.

The start of the facility, including the construction of the first powerhouse, led to the construction of a new wharf at St. Alban’s, an airport nearby and a road linking Bay

d’Espoir to Bishop’s Falls, in addition to the project work. About 1,800 people were employed. Nearly 95 per cent of workers on the project were Newfoundlanders.

It did not go off without a hitch, as explained in the book published in 2000 by the Silver Lights Club — a group of retirees and employees with 25 or more years of service with Newfoundland and Labrador Hydro. The project faced labour troubles and a worker strike. The date to start producing power was delayed.

With that said, “the construction of the Bay d’Espoir hydroelectric development and the high-voltage transmission network became the jewel in the crown of Newfoundland and Labrador Hydro.”

Today, Bay d’Espoir as a whole still stands as a long-life asset, one relied upon to provide power for customers around the island.

Once completed, the power plant at Muskrat Falls will take over Bay d’Espoir’s No. 2 spot in terms of capacity for power generators in the province.

Bay d’Espoir will continue on.

In addition to requests for parts and work in yearly capital budgets, Hydro representatives have made clear the intention propose construction of a new 230kv power line, to bring more Bay d’Espoir power to the Avalon Peninsula.

The power line is expected to cost $268 million over five years.

The proposal was filed with the PUB, retracted and has yet to be made again. However, Hydro’s 2013 capital budget proposal makes repeated references to the project and commits Hydro to filing again at a later date.

afitzpatrick@thetelegram.com

Organizations: Newfoundland and Labrador Hydro, Public Utilities Board, Newfoundland and Labrador Hydro.During The Telegram Silver Lights Club

Geographic location: Newfoundland, Holyrood, Falls

  • 1
  • 2
  • 3
  • 4
  • 5

Thanks for voting!

Top of page

Comments

Comments

Recent comments

  • John Smith
    October 21, 2013 - 06:25

    No one talks about Bay D'Espoir anymore, although, at the time many opposed it...sound familiar? Same will hold true for muskrat 99% of the opposition is purely political. Oh...and does anyone proof read articles anymore?

  • Brad
    October 16, 2013 - 00:29

    is that 600 megawatts per day? per week? just curious.

  • Fred Penner
    October 15, 2013 - 16:02

    One day, Muskrat Falls will be even more valuable.

  • Leslie Wilmott
    October 13, 2013 - 13:41

    I really enjoyed your story on the Bay d'Espoir power plant. I worked at that project during my university years, one summer driving a rock wagon, a PR619, then another summer with Shawmont Engineering doing laboratory soil testing and another time working in the warehouse and doing some expediting. I remember one time being about 12 feet down in a hole taking soil samples, when the sides started to cave in on me. Luckily the backhoe driver was in his seat and got the shovel down to me so that I could grab hold of the teeth and be lifted to safety.

  • lonenewfwolf
    October 12, 2013 - 08:24

    the reason the 230kV line has not been approved is b/c it's all that's reqd to make the island system operate smoothly. no need for muskrat or any of the rest of it. we've been scammed. the avalon power demand could be met by adding this line which will enable the already excess power in central to flow to the expanding avalon population. ask a power engineer.