Long Harbour camp delays have workers waiting on jobs

Preliminary work is seen at the site of the nickel-processing plant in Long Harbour in this 2010 photo. Delays in completing a construction camp at the site has left more than 80 camp support workers — such as cooks, bakers and dishwashers — waiting for their jobs to begin, according to the union representing them. File photo by Joe Gibbons/The Telegram

Preliminary work is seen at the site of the nickel-processing plant in Long Harbour in this 2010 photo. Delays in completing a construction camp at the site has left more than 80 camp support workers — such as cooks, bakers and dishwashers —...

Published on March 25, 2011
Published on March 25, 2011
Daniel MacEachern  RSS Feed
Topics :
Hotel and Restaurant Workers Union Local , Long Harbour , Bay Bulls

Construction delays have hotel and restaurant workers waiting on jobs in the construction camp for Vale’s nickel-processing plant in Long Harbour.

Pat McCormick, business manager for Hotel and Restaurant Workers Union Local 779 in Bay Bulls, said there are 86 members of the union waiting on jobs that were supposed to start between March 14-21 — cooks, bakers, dishwashers, “whatever’s required to operate a camp,” he said.

About a quarter of them gave up other jobs to work at the camp, he said,

Bob Carter, Vale spokesman, said the project is going well, but acknowledged that the camp’s potable water system is behind schedule.

He said half of the camp’s 500 rooms are ready to go, with the rest expected to be ready for occupancy in two to three weeks.

“We’re currently commissioning and flushing the camp’s potable water system, and that should be operational in early April. At that time we will hand that over to the camp operator, and they will do their own flushing, cleaning, and getting the kitchen in particular ready for occupancy.”

Carter said occupancy will start once the camp has the required permits, which are largely dependent on the potable-water system.

“Right now, we basically think we’ll be using the camp towards the latter part of next month,” he said.

The sewage-treatment plant will be completed in early May, said Carter, who added that Vale has regulatory approval to dispose of camp sewage off-site until the camp’s sewage plant is ready.

McCormick estimated that about one-quarter of the 86 workers quit other jobs to start working in the Long Harbour construction camp.

“They had a problem with getting water to the camp,” he said, acknowledging that construction delays on major projects aren’t out of the norm. “It’s frustrating for everybody, but it’s the name of the game. What can you do?”

dmaceachern@thetelegram.com

Twitter: TelegramDaniel

Comments

  • Username
    gary
    - March 25, 2011 at 08:36:00

    That just blows my mind !!!! 1/4 of them quit their jobs and now they are complaining !!! Just shows da greed the union people have... Quit a job so it shows on the books you are not working, thus your name goes back on the list @ the union office so you can get on site....

    Submit a comment

Submit a comment

Submit a comment (we keep all emails private)
Agreement

We ask that users remain courteous. You may not post insulting, discriminatory or inappropriate content, which may be removed at our discretion. We are not responsible for user content and opinions. Use of this site as well as content submission & ownership are governed by our Conditions of Use and Privacy Policy.

Member organizations should be non-profit in nature, and promote legal activities. Any organization found promoting illegal activities or commercial products or services will be deleted from the site.

I agree with these conditions.

Advertising

Newsletter

Please enter your email to receive our free newsletter

Subscribe to news alerts
loading...

Tely Twitter

Advertising