BILL BLACK: Beware of governments touting bold, costly projects

Bruce MacKinnon's cartoon for Nov. 1, 2012 on the beginnings of the Muskrat Falls debacle.
Bruce MacKinnon's cartoon for Nov. 1, 2012 on the beginnings of the Muskrat Falls debacle.

STORY CONTINUES BELOW THESE SALTWIRE VIDEOS

Pro-Palestinian encampment at Dalhousie University - May 13, 2024 | SaltWire #news #halifax #protest

Watch on YouTube: "Pro-Palestinian encampment at Dalhousie University - May 13, 2024 | SaltWire #news #halifax #protest"

Have you had a good look at your electricity bill lately? Some of the power you are paying for now will not be received for 35 years.

The Muskrat Falls power project is being built by Nalcor, a provincially owned utility. It is horribly over budget and behind schedule. This should not be a big surprise. Nalcor had never managed a project of that size. Have a care for our friends in Newfoundland and Labrador who will be paying for the many billions of overrun there.

Nova Scotia’s involvement through NSPML, an Emera subsidiary, is to provide the necessary transmission from a point in Newfoundland across the Cabot Strait and all the way through Nova Scotia to New Brunswick. Called the Maritime Link, this will serve Nova Scotia and enable the transmission of power to New England markets. The power generated by Muskrat Falls will be more than the Atlantic provinces can use.

The Link cost $1.577 billion plus $210 million of borrowing costs during construction. Of this, 70 per cent was borrowed, with a low interest rate which benefits from a government of Canada guarantee. The remaining 30 per cent was equity provided by Emera, on which it will earn a nine per cent return. The payments start at $43 million per year and will gradually reduce as the project cost is amortized.

Maintenance costs for the link are already $18 million per year.

At the time the project was being advocated, it was clear that the Muskrat power was not needed until 2020. Nevertheless, Nalcor insisted that the contract be effective at the end of 2017 and Nova Scotia acquiesced. Emera had the link completed by the end of 2017. The power will not arrive in Nova Scotia before sometime in 2021.

That it would not be used for at least three years costs Emera a penalty each year of $10 million less a small amount for the cost of transmitting power from Nova Scotia to Newfoundland. On the other hand, it lengthens the time over which it will receive its nine per cent return.

The cost to ratepayers so far has been $109.5 million in 2018, $111.5 million in 2019, and $144.5 million in 2020. This is scheduled to increase to $164.4 million in 2021 and $161.9 million in 2022. This year’s cost is more than $150 per Nova Scotian.

If the total delay is three years, the power not received in 2018-20 will be added on at the end of the 35 years from the starting date. Your grandchildren can thank you.

Readers may wonder how we got in such a mess. There is plenty of blame to go around.

In 2013, Emera persuaded Nova Scotia’s NDP government that the project was both an economic and environmental winner. It was clear from their clumsy efforts to explain it that neither Premier Darrell Dexter nor any of his ministers had any understanding of how the contract would work.

It is noteworthy that in Newfoundland and Labrador, the Progressive Conservative government, which also did not understand what they were getting into, chose to bypass their electricity regulator — the one venue where they might have received well-informed advice.

Dexter took a different route, choosing instead to put the Utilities and Review Board (UARB), the Nova Scotia regulator, in a straitjacket. Its legislation said that:

“The Review Board must approve the Maritime Link Project if, on the evidence and submissions provided, the Review Board is satisfied that the project … represents the lowest long-term cost alternative for electricity for ratepayers in the Province …”

What that meant was that any competing ideas for providing power had to compare against what Muskrat would provide, rather than both comparing against Nova Scotia’s needs.

The NDP were defeated in the 2013 election before the final UARB approval process was completed. The Liberals clearly did not understand the file either and their intervention was shambolic. They had a chance to step us back from the brink and failed to seize it.

The UARB also missed a chance. Notwithstanding the legislated constraints, it could have done a better job of protecting ratepayers from the cost of the entirely predictable delay. They could have required greater delay penalties to NSPML, or through them, Nalcor.

Looking forward, there is not much chance of the current Nova Scotia government announcing a big green project that it does not understand.

But worry about Ottawa. Here is what Justin Trudeau had to say about the federal Liberals’ intentions for the upcoming throne speech: “Around the world, a consensus is emerging that the time has come to think boldly and rebuild even stronger… Countries like Canada that have a strong fiscal position must invest to help people get through this crisis.”

If the Liberals can make a mess of handing out cash to volunteers, it is scary to think how they will manage bold ideas.

Op-ed Disclaimer

SaltWire Network welcomes letters on matters of public interest for publication. All letters must be accompanied by the author’s name, address and telephone number so that they can be verified. Letters may be subject to editing. The views expressed in letters to the editor in this publication and on SaltWire.com are those of the authors, and do not reflect the opinions or views of SaltWire Network or its Publisher. SaltWire Network will not publish letters that are defamatory, or that denigrate individuals or groups based on race, creed, colour or sexual orientation. Anonymous, pen-named, third-party or open letters will not be published.

It has been our privilege to have the trust and support of our East Coast communities for the last 200 years. Our SaltWire team is always watching out for the place we call home. Our 100 journalists strive to inform and improve our East Coast communities by delivering impartial, high-impact, local journalism that provokes thought and action. Please consider joining us in this mission by becoming a member of the SaltWire Network and helping to make our communities better.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT

Local, trusted news matters now more than ever.
And so does your support.

Ensure local journalism stays in your community by purchasing a membership today.

The news and opinions you’ll love starting as low as $1.

Start your Membership Now